Home Forums Discussion Projects

Viewing 3 posts - 1 through 3 (of 3 total)
  • Author
    Posts
  • #416206 Reply

    some of my task do not have the correct duration calculated not all of them does anyone know what is causing this?

    #416208 Reply
    Larry ChristofaroLarry Christofaro
    Participant

    Hi Bill, that can be due to calendar changes. Are you using multiple calendars for tasks/resources?

    #416398 Reply

    Do you have resources assigned to summary tasks? They should only be assigned tot he lowest levels.

Viewing 3 posts - 1 through 3 (of 3 total)
Reply To: Projects
Your information:




− 2 = 2