As the title reads how do i show the baseline progress? I want to compare it with my actual progress.
I set the baseline1 and then under activity details checked ‘actual’ and then added a column ‘% progress’ and updated each activity with some percentage.
I can see the overall project progress but that is the actual progress. How do i compare it with the baseline progress? I have put baseline start and finish columns but i don’t find % baseline progress column?
Am i doing something wrong? I use P6 so i don’t really know much about msp.
Any help would be appreciated. TIA
Note: i have not put any resources do i need to assign resources? but then it would be similar workflow to P6. How does msp make my work easier?