Home › Forums › Microsoft Project Discussion Forum › Report that shows unlinked tasks and other problems
Tagged: Microsoft Project 2003, Primavera, reports, Tasks
Hi All,
A person that used to use Primavera and now uses Project 2003 asked me is there a report in Project 2003/2007 that shows unlinked tasks and other “work to be done” so to speak. I did show them how to add the Successors column and filter for blanks row ( as all tasks should have a successor I think) but they want a report which prints out.
Just wondering if there is an add on etc
Thanks
Bert
I use the MS Project auditor add-in available for $30 at qpmusa.com/QSA-Schedule-Auditor.html for terrific results that show not only missing predecessors and successors, but many other structural problems in your schedule.