Resource calendar issues on Project professional

Home Forums Discussion Forum Resource calendar issues on Project professional

Viewing 4 reply threads
  • Author
    Posts
    • #416703
      Scott
      Guest

      When selecting resources I lose a day over the allocated duration. It shows day one as 0.63 and the last day 0.37 equating to a full day lost. How can I remedy this? I have checked the calendars and from what I can see both the project and resource ones match.

      Thanks

    • #416705
      Larry Christofaro
      Participant

      Scott, I would suggest looking at two things. 1. Go to Options / General tab and set the Date format to include the time. 2. Look at the Options / Schedule tab and make sure that the Calendar options settings, specifically Hours per day matches the calendar. Hopefully that can help diagnose the issue.

    • #416706
      scott gillan
      Guest

      Thanks, I’ll have a look and see how it goes.

    • #416707
      Daryl Deffler
      Guest
    • #416730
      scott gillan
      Guest

      Thank you, That’s helped a lot. I’m looking to use our project professional as a resource tracker over multiple projects, but all resources and allocated projects on the same file. Is this possible? I used a previous version of project in this way but, with the developments that have been made, I’m struggling to make this version work effectively. Thanks again for any help.

Viewing 4 reply threads
  • You must be logged in to reply to this topic.