  • #411649 Reply

    Timia Harris
    Member

    Is there a way to view each individual’s hours by WP? I tried creating a new group by WP, then by resource but it won’t group individually. Anyone have a solution?

    #411659 Reply
    Sai Prasad
    Sai Prasad
    Participant
    • Community Leader
    • Forum Pro

    Timia – Change the view to Task Usage and apply the group created.

Viewing 2 posts - 1 through 2 (of 2 total)