Restricting execution of a task to a pre-defined date range

Home Forums Microsoft Project Discussion Forum Restricting execution of a task to a pre-defined date range

Viewing 2 reply threads
  • Author
    Posts
    • #412956
      Pat Butler
      Guest

      In MS Project 2016, is it possible to restrict execution of tasks to date ranges? E.g. certain tasks cannot be performed between two dates?

    • #412958

      Pat;
      While I’ve never had to do this, I would suggest trying a task specific calendar. Since your request is for the task to NOT be worked on between certain dates, you can make those days non-working days in the task calendar.
      Hope that helps

    • #412961
      Pat Butler
      Guest

      Thanks Daryl, I’ll give it a try