Home › Forums › Discussion Forum › Scheduling equipment as resource
Tagged: equipment, Resource, scheduling
Hi-
I was wondering if anyone knew of an easy way to schedule equipment as a resource so the task doesn’t break. Even when scheduling to available date, it will break the task. I need it to stay the entire duration because the activity requires special laboratory equipment. Any ideas would be greatly appreciated! So far I have been manually dragging the other end of the task back to attach it.