We currently work an 10 hour day x 11 day fortnight, our crews have every second weekend and the following Monday off. So, 11 days on, then 3 days off (Saturday, Sunday, Monday). working 10 hours per day. I haven’t been able to work out which calendar to use, and how to adjust it correctly to give me what I need?