Setting up an 11 day, 10 hour fortnight in Project professional.

Home Forums Discussion Forum Setting up an 11 day, 10 hour fortnight in Project professional.

Viewing 1 reply thread
  • Author
    Posts
    • #416142
      Mark Gaudry
      Guest

      We currently work an 10 hour day x 11 day fortnight, our crews have every second weekend and the following Monday off. So, 11 days on, then 3 days off (Saturday, Sunday, Monday). working 10 hours per day. I haven’t been able to work out which calendar to use, and how to adjust it correctly to give me what I need?

    • #416145
      Thomas Boyle
      Guest

      The same question (almost) was answered a few weeks ago on technet.
      Technet question on work schedule

Viewing 1 reply thread
  • You must be logged in to reply to this topic.