Home Forums Discussion Shading time Zones

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #5142
    Avatar photoCommunity
    Keymaster

    Olympics

    How can I shade a time period on the Gantt Chart.

    So for example I’m doing a plan to run throughout the year but I’d like to shade a couple of 2 week periods for the Olympics and Paralympics so I can see at a glance which of my tasks will be taking place during these times. 

    I don’t want to fudge it using non working time shades etc.

    #10600
    Avatar photoCommunity
    Keymaster

    You can use “draw” under “tools” to insert a rectangle in the Gantt bar area.  Then right-click the rectangle, select “order”, and select “send to back”.