Hi
Is it possible link the inserted subprojects to master project?
Explain: I have inserted a subproject (summary task with 5 subtasks) on a master project.
I pretend that this subproject have the same duration of master project althought the variances will be.
If i increase the duration of the master project then the subprojecct automatically will also increase.
Subproject are linked to master projects by default, no? The master shows the duration of accumulated project durations + the master project duration.
Hi Jigs
I did not explain my issue correctly:
I have a master project with 100 activities/tasks with a milestone task of conclusion.
Later i insert a small subproject (5 tasks)
I would like to have dependencies between the last task of my master project and my subproject summary task.
Then if i track the tasks of master project will have automatically impact on the subproject inserted.
Other way How can i constraint (start and finish) the subproject with the master project?
Regards,
Carlos Santos
Have you tried not linking the Subproject summary task, but the first task in the subproject group?