Home › Forums › Discussion Forum › Summary dates in MSP 2003
Tagged: Microsoft Project 2003
I have some subprojects that show later project finish dates when in the master (where they are inserted) than they show on each individual file. For other reasons, I’m using ALAP if that makes a difference. I can’t tell why they’re later in the master. There are no late date constraints in any of my subprojects. Any suggestions?
Hi Jack,
I am not running 03 so I cannot test this, but have you checked your calendars? It could be that the master is set with a different calendar or the hours per day/week may be an issue?
Cheryl, I am using the same calendar but thanks for your effort. Does anyone else have any suggestions?