Home › Forums › Discussion Forum › Summary Progress Display in Gantt View
Tagged: Ganntt View, Gantt Chart
I have a master file that contains approximately 20 sub project files. I am using the Project summary bar to show progress at the project summary level. Can someone tell me how to show the progress bar inside the summary bar, as is possible with individual tasks?Whenever I try to put these bars on the same line in the gantt view, the summary either block, sits on top of the progress bar, or the progress bar is below the summary.
I am yet to figure out how this is done.
Cheryl
I had this same question and was answered on another board. Thanks John.
You will need to look at the order in which the bars appear in the Bar Styles Dialog. Simply insert the progress bar beneath the summary bar and this should get what you are looking for.