Loading...
Quick Links

Sync function in MS Project 2010

Home Forums Discussion Sync function in MS Project 2010

Viewing 3 posts - 1 through 3 (of 3 total)
  • Author
    Posts
  • #17361 Reply
    Joe Fletcher
    Participant

    We are using MS Project 2010 (server),  on my Save/Send function I don’t have the availability to Sync to SharePoint, does that have to be turned on somehow?

    #17545 Reply
    John Riopel
    Participant

    When you are using Project Server the sync to SharePoint function is disabled, since you are saving the files to the Project Server database.  The sync to SharePoint function is for users that do not have Project Server.

    #18287 Reply
    Joe Fletcher
    Participant

    Thanks!

Viewing 3 posts - 1 through 3 (of 3 total)
Reply To: Reply #17545 in Sync function in MS Project 2010
Your information: