Home › Forums › Discussion Forum › Task created after baseline set
Hello everybody
I have a project file where some activities were added after the baseline was set.
In fact some of the tasks where further detailed and indented; so as it has now been made a summary task with baseline but the detailed ones does not has a baseline date.
can i copy the baseline dates from the summary task and paste the baseline dates into the detailed tasks?
Your situation is common and can be a challenge to get right. You might want to see if you can find a good blog on the subject, but here’s a short version. Select only those new tasks and any tasks dependent on those tasks, then set baseline for selected tasks and rollup to summaries. It requires a properly managed project (no deleted baselined tasks, etc.). Make sure you validate the rollup to what you would expect (total hours, total costs, etc.).
Hi Larry
Thank you for the advice.
I’ll try it and feedback you.