Loading...
Quick Links

Task Name Disappears-requires software shutdown and reopen

Home Forums Discussion Task Name Disappears-requires software shutdown and reopen

Viewing 5 posts - 1 through 5 (of 5 total)
  • Author
    Posts
  • #4854 Reply
    Community
    Keymaster

    Is anyone having the task name disappear on them when working with their schedule?  It seems to happen most often when I am toggling between different views (in my case Gantt and Resource Usage) but I am also collapsing or re-collapsing summary tasks.   I have not lost data, if I shut down the software then open it and the file back up the task name reappears.

    #6027 Reply
    Community
    Keymaster
    Robin,
    I looked in the Project forum and didn’t find anything on this error.  Not sure what version you are using.  I might suggest making sure you are on the most current version and/or uninstalling and reinstalling the software.  Sorry, but require a bit of time.
    Hope that helps,
    Larry Christofaro
    #6028 Reply
    Community
    Keymaster
    This occurs almost weekly with my projects. I am using a master project with a master resource using project professional 2010. What are you using and do you use a master project. I have reported this on several web sites with no answers as to what the fix may be.
    Phil Horton
    #300686 Reply
    Tim
    Guest

    Phil,

    Any solution to your question? Was there any way to retrieve the task names? I have a major project schedule with 120 sub-projects. Microsoft Project shut-down after an error, and when I reopened all dates were still present but the task names were missing!! Please help if you have any information on this!! This will be detrimental if I lose all of this information.

    Tim

    #300855 Reply

    Hi,

    sometimes filters do cause this problem. Try removing the filters.

Viewing 5 posts - 1 through 5 (of 5 total)
Reply To: Task Name Disappears-requires software shutdown and reopen
Your information: