Tracking Progress tasks with costs and work resources assigned / PV (BCWS) VALUE

Home Forums Discussion Forum Tracking Progress tasks with costs and work resources assigned / PV (BCWS) VALUE

  • This topic is empty.
Viewing 1 reply thread
  • Author
    Posts
    • #414289
      Carlos Santos
      Guest

      Hi

      I have a Project with more than 300 tasks.
      I made the “mistake” assigned both, costs and work resources, to each task.
      I said “made mistake” because when tracking progress I realized that the costs resources were not updated. I had to manually update the costs in the Task Usage View (tracking table, actual cost field/column).This is how MS Project works. Ok. Next time is better add tasks with only costs resources.
      My question/Issue is: After Tracking, in the Earned Value Table, the value PV(BCWS) IS ALSO NOT UPDATED. This field I can do nothing!
      Solution?

      Regards,
      Carlos

    • #414290
      Carlos Santos
      Guest

      Not only the PV (BCWS) value, the AC (ACWP) Value is also not updated.

Viewing 1 reply thread
  • You must be logged in to reply to this topic.