Home Forums Discussion Unique ID’s

This topic contains 1 reply, has 2 voices, and was last updated by Larry Christofaro Larry Christofaro 4 days, 17 hours ago.

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #413959 Reply

    Gerald

    I am running MS Project 2016 and using Milestone Pro for charts. When I cut and paste task within the schedule, MSPro assigns a new UID. Is there a way to keep the original UID numbers? The schedule is quite large and would not be practical to drag the task a 1000 line up or down.

    #413961 Reply
    Larry Christofaro
    Larry Christofaro
    Participant
    • Expert
    • Forum Pro
    • Ombud

    Unfortunately that is the only option available. You can drag the task(s) to the bottom of the page and it will continue at a pretty fast pace. Otherwise close summary tasks. Sorry, best I can suggest.

Viewing 2 posts - 1 through 2 (of 2 total)
Reply To: Unique ID’s
Your information:




+ 42 = 47