Should the max hours per timesheet be 168 (24×7) or 999 unlimited if Team Resources are defined ?
Thanks John
User preference. I tend to like some limitation to catch glowing mistakes, but depends on your process. If you close timesheet periods and people are required to enter in future weeks then that won’t work.
I will think about … likely the 168.