I’d like to use a weighted milestone technique to “feed” earned value data to an EVM tool. However, if I load resources on to a milestone, it ceases being a milestone. I could assign cost values (rather than resources) on the milestones and earn value equivalent to the costs as the milestones are completed. That seems to defeat the rationale of using a resource-loaded logic network to develop the time-phased budget in the first place. Any suggestions? Has anyone successfully used a resource loaded network and figured out how to handle the weighted milestone EV technique as well?