Weighted Milestones EV methodology in MS Project?

Home Forums Discussion Forum Weighted Milestones EV methodology in MS Project?

Viewing 1 reply thread
  • Author
    Posts
    • #4832
      William Holbrook
      Keymaster
      I’d like to use a weighted milestone technique to “feed” earned value data to an EVM tool.  However, if I load resources on to a milestone, it ceases being a milestone.  I could assign cost values (rather than resources) on the milestones and earn value equivalent to the costs as the milestones are completed.  That seems to defeat the rationale of using a resource-loaded logic network to develop the time-phased budget in the first place.  Any suggestions?  Has anyone successfully used a resource loaded network and figured out how to handle the weighted milestone EV technique as well?
      Thanks for any suggestions.