Home Forums Discussion ‘What-if’ analysis by replication, modification, and inactivation didn’t work

Viewing 1 post (of 1 total)
  • Author
    Posts
  • #418381 Reply

    I tried to run a What-if analysis by

    1) cloning a task with copy/paste (the pred/succ were not cloned)
    2) used ‘fill-down’ to clone the pred/succ values
    3) deleted one of the predecessors in the clone
    4) inactivated each clone to examine the impacts

    What I found is that the knock-on effects of deleting the predecessor in the clone are different than eliminating that same predecessor in the original task when each one is ‘active’. This surprises me, but maybe I shouldn’t be. Does anyone have any idea why the two versions would have different downstream effects?

    BTW, this is in a master project with 4 sub-projects in Project Pro 2016.

    Thanks,
    Dan

Viewing 1 post (of 1 total)
Reply To: ‘What-if’ analysis by replication, modification, and inactivation didn’t work
Your information:




7 + 2 =