Why is Level Selection disabled?

Home Forums Discussion Forum Why is Level Selection disabled?

Viewing 5 reply threads
  • Author
    Posts
    • #418497
      dan schaeffer
      Participant

      I’m using a main project with 5 sub-projects. One of the sub-projects is a resource pool. When I try to level two tasks from different sub-projects the ‘Level Selection’ menu is disabled? Why would that be the case?

      Thanks,
      Dan

    • #418498
      Daryl Deffler
      Guest

      Dan,
      Its been a while, But I believe you need to select more than one task, then select the Level Selection option. Meaning you need to make the selection before you try to click level selection.
      Hope that helps

    • #418499
      dan schaeffer
      Participant

      Daryl,

      I wish it were that simple. I’m trying to level two tasks from different sub-projects and it’s not enabling.

      Any other ideas?

      Thanks,
      Dan

    • #418533
      ben howard
      Guest

      Do either of the tasks have actual start dates? Can you post an image to show?

    • #418534
      dan schaeffer
      Participant

      Ben,

      Nope. They’ve both got an Actual Start date = N/A. I’ve posted a screen grab here. Let me know if you can’t read it.

      Thanks,
      Dan

    • #418600
      dan schaeffer
      Participant

      Any hints Ben?

Viewing 5 reply threads
  • You must be logged in to reply to this topic.