    We recently upgraded to Project server 2010.  After that we could not work in offline mode on projects in cache.

    After a long investigation and troubleshooting the cause was discovered to be the Enterprise Global.  This files requires an upgrade also. For more information refer to http://technet.microsoft.com/en-us/library/gg502585.aspx

    Regards.

    #10408 Reply
    Community
    Keymaster

    Thank you for sharing your experience and research.