Hi Rich,
Thanks for your input.
P.s. I cant access that article you are referring to.
Kennet
Thanks for replying Daryl, Larry and Oliver.
I will study your recommendations and get back if necessary.
Br. Kennet
Hi Carlos,
I didn’t try your way but its true that tasks set up as fixed duration distribute work for all allocated resources
My problem was related to tasks set up as fixed work.
Br Kennet
Hi Daryl and Sai,
Thanks for that clarification.
Br Kennet
Hi Sai,
Its not because the other resources have non-working days.
Let me explain.
Task: FD – Duration 1 day – 2 resources
Ress M-T-W-T-F
KB 3-0-0-0-0
Gru 5-0-0-0-0
Same task, but duration is changed from 1 to 5 days.
Ress M-T-W-T-F
KB 3-0-0-0-0 (Work is NOT distributed – WHY?)
Gru 1-1-1-1-1 (Work is equally distributed)
It seems like only the highest workload (5 hours in this case) is equally distributed.
Hope this make sense to you.
Br Kennet
Hi Sai,
Sorry, I mean Fixed work and not fixed duration.
How can I upload a screenshot?
BR Kennet
Hi Larry,
Thanks for answering.
I still cant solve my problem – I hope you will give it another shot.
when leveling the schedule I sometimes end up with a few summary tasks that have a duration of several month, though the expected duration is more likely to be a week or two.
Is it possible to send you a screen dump or a Project file? Its not that easy for me to explain the problem without pictures.
BR Kennet
Daryl
Sorry if I didnt explain myself clearly enough. YES, I´m getting an error message when during the leveling process. The message says: “Project cannot solve the overallocation of “Ole” on Tue 01-05-2018″
So, I get an error message during the leveling process when the timeframe is set to “week by week” and I dont get an error message during the leveling process when I change the timeframe to “Minute by minute”
I´m very well familiar with your 13 articles about the leveling process. Much appreciated by the way 🙂
Kennet
Thanks Daryl,
I understand what you are saying, but I still dont understand why Project cant level the plan with the setting “Week by Week” or “Month by month” but it can when I change the setting to “Day by day” or “Hour by hour”?
Hope you will give it another shot 🙂
Kennet
Thanks a lot Daryl.