cbass1224

@cbass1224

Active 2 days, 23 hours ago
  • I decided to try in a different schedule and have the same result. It seems like in order for summary tasks to roll up from one level to another on the Gantt chart, at least one task on the lowest level has to roll up as well. Otherwise no bars show up at all. Is there a setting for that? Or is it a bar format issue?

  • I have a different summary task roll up issue. I have a set of tasks on level 4, that I don’t want to roll up. I have the level 3 summary task set to roll up to the level 2 summary task. Level 2 is also set to roll up. But nothing rolls up to level 2, unless I mark at least on level 4 task to roll up as well. Then all level 3 summaries roll…[Read more]

  • I am making a schedule for an upcoming week long shutdown with multiple shifts. The night shift will run from 6pm-6am. So, some summary tasks will begin on one day and start on the next. For some reason, whenever this happens the duration is shown as zero and they are being formatted as both summary tasks and milestones. Any ideas why?

  • cbass1224 replied to the topic Progress Lines in the forum Discussion 5 months, 2 weeks ago

    Thank you for the reply. Right now, I’m setting up a schedule for a project that hasn’t really begun. I’m trying to get the formatting correct before I fill in all of the detail. Then I’ll populate all of the future tasks as they need to get completed to finish each phase on time.

    My company is accustomed to seeing schedule status with a…[Read more]

  • cbass1224 started the topic Progress Lines in the forum Discussion 5 months, 2 weeks ago

    My company is all about progress lines. So, I’m trying to figure out how to get it to work correctly. It is really easy to turn the progress line on in Project 2016. But, it doesn’t always show the status accurately for Summary Tasks. If the status date is after a series of tasks that have not started yet, the progress line jumps all the way to…[Read more]

  • I’m formatting summary tasks based on the name. Thanks for your input.

  • Thanks. I have to work with company IS to try to get it fixed. We tried repairing the App but that didn’t work. I’ll see if I can find out if there’s an update available.

  • No, I had not. And that was the problem. Thank you very much!

  • Hello, all. I cannot get bar heights to change on screen in Project Professional 2016. It seems to be a problem with my laptop. The bars will change in the same files opened on other computers. All of them running Windows 10. Has anyone had this problem? What is the cause/fix?

    Thank you!

  • Hello, all. Does anyone know how to flag summary tasks? I want to flag them based on the summary task name. I would have thought either [Name]=”” or [Task Summary Name]=”” would do it. But neither work. [Name] only applies to actual tasks with that name, and [Task Summary Name] applies to all subtasks underneath the summary with that name.