    • #406518

      Great, Thanks Larry! I found that you also need to change the “To” setting (right column) to % Complete. With this a progress bar is being shown across the summary task with the % complete

    • #406516

      I know how to show the % Complete as a number (left or right of a summary task). What I am interested is a progress bar showing underneath the summary task bar