Fletcher Hearns is the Director of Technology Solutions with Edwards Performance Solutions (www.EdwPS.com). He is responsible for the implementation, of Enterprise Project Management (EPM) solutions for Edwards’ clients, as well as overseeing as well as overseeing the custom application development performed at Edwards around enterprise solutions and Microsoft Project (Desktop & Server) and SharePoint. Fletcher is also one of the leading trainers at Edwards in various aspects of Project Management and the use of project management tools.

Forum Replies Created

Viewing 1 post (of 1 total)
  • Author
    Posts
  • #483527 Reply
    Fletcher Hearns
    Participant

    Kris,

    The main problem with tracking resources at the summary level is that is not where the work is actually done. It will make the tracking of cost/work/time at the task level more difficult if that is required.

    MS Project wants to roll everything up from the lowest elements of the project schedule to the Summary task to the Project Summary task so you might have to work around that too.

Viewing 1 post (of 1 total)