I use these Custom Fields on Task Bars often (MSP 2013).
TEXT1 : [Name] & ” – ” & ([Duration]/480/5) & ” wks ”
TExT2 : ProjDateConv([Finish],pjDate_mmm_dd) & ” (” & ([Duration]/480/5) & “wks) ”
TEXT3 : [Name] & ” (” & ProjDateConv([Start],pjDate_mmm_dd) & “) “
Tried your method and it worked perfectly… thank you… I have been looking for this technique for some time. KMD
Thank you for this.
I did create the View with a “Task Range Filter” applied and the system (MSP 2013 Std.) does work however, the Task Range (Tasks Between Task ID 50 and Task ID 100) is not stored, so the system pops up with the Task Range Dialog Box asking for the Task IDs. I suspect this might be the same for Date Filter too…. although other filters like “Milestones” did work OK.
KMD
Is there a method to apply to filtering as well as sorting ?
For example, can a filter be applied and saved as part of the current view and then save as “Filtered View”.
Specifically : Filter = Show Tasks Between Task ID 50 and Task ID 100.