Sai Prasad replied to the topic CP ends somewhere in the middle of the project in the forum Discussion 5 months, 2 weeks ago
As task #299 is not the last task in your project, check the following:
1. All tasks except the last task and first task should have at least one predecessor and successor
2. Check if you have Finish no later than, Start No late than constraints on tasks. This can affect the calculation of the slack
3. Check if you have deadlines on tasks, which…[Read more]
Sai Prasad replied to the topic MS Project and Sharepoint in the forum Discussion 9 months, 1 week ago
Yes, you can sync a list of tasks with SharePoint. Your team members can view the schedule and update their work in SharePoint, and you’ll see the changes in Project. And vice-versa. Do expect, as per the documentation, if there are more than 100+ tasks the sync will be slower. Know more on how to use this feature at h…[Read more]
Sai Prasad replied to the topic Options for Selecting more than one Outline Code in the forum Discussion 9 months, 2 weeks ago
Unfortunately, you can’t do it. Custom fields and outline codes, in general Project, doesn’t allow you to choose more than one value in the list.
You can use multiple fields and make a selection in each one and then combine the data in another field. As an example, you’ve created a lookup in three Text columns (Text1, Text2, and Text3). A…[Read more]
Sai Prasad replied to the topic Connexions features when printed to PDF in the forum Discussion 9 months, 2 weeks ago
Hi, I have Project 2016 and 2019, and don’t this issue you just reported. May I know the Acrobat PDF version and Project version to find why this is occuring.
Sai Prasad replied to the topic Critical Path not showing in the forum Discussion 1 year, 1 month ago
Thanks @Ryan for sharing your solution.
Sai Prasad replied to the topic How to clean up global.mpt in the forum Discussion 1 year, 6 months ago
Check this link https://saipower.wordpress.com/2010/06/06/six-common-questions-about-global-mpt/#:~:text=Question%20%234%3A%20Where%20is%20Global,Office%5COFFICE11%5C1033%20folder. It answers your question
Sai Prasad replied to the topic Reports for Deadlines and Calendar in the forum Discussion 1 year, 8 months ago
I suppose your question is on Project desktop client. On your first question on report on deadlines, create a filter with Deadline not equals NA (see this picture https://i.imgur.com/BwsFHwq.png for steps). I don’t get your later question on calendar view, please elaborate
Sai Prasad replied to the topic Locking Tasks in the forum Discussion 1 year, 8 months ago
Locked flag is used for Project Online / Server to prevent team members from entering additional time on a completed task. Though there are alternatives available like macros, customizing filters and views, it will not prevent users from not editing the tasks.
Sai Prasad replied to the topic Relation between Resource Max Units & Resource availability in the forum Discussion 1 year, 9 months ago
Hi Koen, This should work. After changing the system date and opening Project, check Current Date in Project > Project Information. Max Units knows today’s date from Current Date field.
Sai Prasad replied to the topic Relation between Resource Max Units & Resource availability in the forum Discussion 1 year, 9 months ago
Max Units (in Resource Sheet) is the availability of that resource on today’s date. This value is calculated from the “Resource Availability” table in Resource Information dialog. It doesn’t consider if the resource is occupied with work or not.
Resource Availability (in Resource Information) indicates the availability of the resource during a…[Read more]