Microsoft® Project Do’s & Don’ts: Including Summary Tasks in Project Sequencing

Microsoft® Project expert Sam Huffman gives us the do’s and don’ts of Project. Each of these 9 videos shows a different problem that Project users may face and demonstrates how to solve that problem. From organizing your outline to leveling resources, Sam Huffman shares his techniques for getting the job done right. Join MPUG to access full-length, live webinar training sessions and hundreds more on-demand.

Including summary tasks in project sequencing can cause a lot of problems if you are not familiar with Projects scheduling process. By the end of this video, you will know what to look for in order to avoid any problems and even find ways to reduce your project schedule.


Want more Do’s and Don’ts? Check out MPUG’s new book: Microsoft® Project Do’s and Don’ts!


Click the links below to see more videos in Sam Huffman‘s Microsoft® Project Do’s and Don’ts series:

Using Elapsed Durations for Team Schedules
Constraining Activities
Organizing Project Tasks Incorrectly
Inadequate Baselining
Scheduling Projects as Late as Possible
Leveling Resources Without Analysis
Incorrect Calendar Association
Assigning Resources to Summary Tasks

Written by Sam Huffman
Sam Huffman first gained insight into Microsoft Project while working as a member of the MS Project development and support team. He has maintained his depth of knowledge of MS Project with each release and is a leading authority in the use and features of MS Project, Project Server and Project Online. Since the early 1990's Sam has honed his instruction skills by delivering training programs to thousands every year. Sam is a frequent content contributor to the Microsoft Project User Group (MPUG) and speaks to groups often about MS Project, Enterprise Project Management and the discipline of Project Management. He was awarded Microsoft Most Valuable Professional from 2010-2017. Check out his blog on MS Project. The softcover version of my newest book Microsoft® Project Do’s and Don’ts is now available for purchase! It is portable, brief and to the point so you can find help when you need it. Through tips, best practices and examples it will help you jumpstart your project!
Share This Post
Have your say!
00
1 Comment
  1. Using the milestone would be best. I’m not saying that you must not use summaries in sequencing – it’s just not something I recommend due to potential scheduling issues such as the one I pointed out.

Leave a Reply