Some of the largest and most expensive projects completed of late have been fraught with huge time & cost overruns. These unexpected delays and expenses cause partial or full project failures with much hardship for all involved!
Yet there have been a few cases where multi-billion dollar projects have been completed on time, under budget and beyond all odds -with a minimum of rework.
Well, reasonably so…
The development of the USA’s Virginia-class nuclear submarine – a collaboration between two fierce competitors (General Dynamics and Newport News Shipbuilding) – is just such a success story. This US DOD project produced modernized submarines that cost far less to build and maintain than the previous model then in service (the Seawolf-class submarine). There were four key innovations that contributed to the Virginia-class project success:
1. Virginia-class submarines were designed using the then new technology –CAD (computer-aided design) – eliminating the mountain of paper blueprints needed to begin the project.
2. Resources from two competing companies were employed in order to cut down on build time – placing them in anunnatural collaboration.
3. A simulator was built to test the design of crucial command components – before installation on the submarine assembly.
4. The interior of the submarine was built in modular parts (some the size of a small house) that could be slid in and out of the hull later on down the road, thus extending overall life expectancy of the class.
By examining these innovations(1) more closely, we can glean our own lessons-learned likely applicable to our own projects, no matter how large or small.
How innovations in technology helps any project manager…
It may seem obvious to use the latest & greatest technology when starting a new project, but that is not always the case. Sometimes project managers like to stick with what they know (works), and also like to play it safe, “If it ain’t broke, don’t fix it.”
This wasn’t the case for Virginia-class planners, as they knew they needed to use technology innovations to bring their project in under budget, and under the intense political scrutiny of 1990’s defense-budget reviews. So they took a gamble, used the new CAD software and went completely paperless for their build plans.
Now while today’s Microsoft Project planner has made great strides in the elimination of all sorts of paper previously employed (by justusing our beloved software), we should also follow the Navy’s lead and holdtechnology reviews. Since new tech arrives almost daily, we should examine new developments in technology before the start of every new project.
For example, if one were starting a project today and haven’t upgraded to Microsoft Project 2016, some thought should be given to how an upgrade might help. If you haven’t looked at Project Online or even Project Server and SharePoint, then one has to ask, why not? But no matter what technology you are using to plan and rollout your projects, it’s changing all the time.
How innovations in collaboration can turbo-charge project finish-times…
As project managers, we are always talking about collaboration (one of the most famous buzzwords of the 21st century), but from what I’ve seen, we rarely innovate in this regard before the start of each new project. I suggest a “collaboration review” before the start of your next project, where your team spends some time discussing how to better work together on the next new thing – take the Navy’s lead here and consider something outrageous and uncomfortable, like collaborating with the competition -one and all for the common good, eh?
That’s what the US Navy did when rolling out the Virginia-class project, and they shaved years off delivery times.
How innovative modular designs can save you time and money…
We tend to think of modularization as something that happens during manufacturing processes, like building “plug and play parts” for phones or cars. But have you ever thought of building project plans in a modular fashion? Fortunately for Microsoft Project users, this is such an easy thing to do – if some foresight is used.
The Master Project / Subproject feature of MS Project is perfect for such an innovation. Consider making your plans modular in nature, so those bits can easily be re-used later on down the line. Hint: the subplans are the reusable bits. That’s what the Navy did with a submarine, so surely we can do that too. The end result will be less time spent reworking old plans to fit new projects, and in short, we’ll just save a lot of time and money.
How innovative simulations can make any project more risk-resistant…
The Virginia-class engineers knew they had no time to design components that would later have to be redesigned because they didn’t quite work when actually installed in the final product. So they built a simulator to test critical component-designs before actually putting them into action. (As an added benefit, personnel who would later have to operate those components, had a shorter learning curve.)
I propose that we all use Microsoft Project to also do the same – by conducting what-if scenarios during any initial project plan design. It’s so easy to do: just run simulations by changing draft plan values inside of MS Project – thus simulating various scenarios, like unexpected changes in resource allocations, schedules or budget. There are great addins to MS Project that do Monte Carlo-type simulations, which assess project risk even before the first task is ever started.
Similar to what Navy engineers did with their simulator, project managers can make their project plans more efficient and less risky by first spending some time running project-plan simulations – before ever putting the plan into play!
So you’re not planning on building a nuclear submarine anytime soon…
Of course, most of us are not planning on building a replacement for the Virginia-class submarine, or any kind of billion-dollar submersible for that matter, but by taking the lessons learned from those that did, we can see how the innovations deployed on that project, can lead to our own – even if our projects are much smaller and less costly.
By innovating our use of technology,new collaboration techniques,modular plan designs and simulations, we too can roll out projects as successful as the Virginia-class nuclear submarine.
(1) See “Cost Estimation Lessons Learned for Future Submarine Acquisition” from James E. O’Harrah, CDR USN, 7 February 2010.
Related Content
Webinars (watch for free now!):
Leveraging Project, Project Server and Project Online for Better Communications
The Basics of Schedule Planning – It’s ALL about Communication
Articles:
Communication: 5 Ways to Improve Your Project’s Lessons Learned
Size Matters (in Plan Communications)
Ask the Experts: 15 Microsoft Project Tips for New Users
steve
Jigs, Thank you for communicating this. New collaboration techniques, modular plan designs and simulations are all major leaps that further the disciplines of project execution!
Jigs Gaton
@steve: agreed – and thx for your comment!
Hessel
I enjoyed your case study, Jim, especially the way you showed how the learnings could be applied to ‘regular’ projects. Do you have an example of a project that you managed in which you applied such principles?
Jigs Gaton
@Hessel, I’ve been busy so it’s taken 1.5 years to answer your question! The answer is actually a few chapters in a book I’ve been writing, but let me say that my mentor during my IBM OS/2 days actually used all of the above as we rolled out the new operating system. We had lots of new technology to play with back then…new coding tools and the earlier versions of MS Project (DOS before Windows) certainly. As for innovative collaboration, just being on a solid network with a color display and an intranet was radical back then. For simulations, we did that mostly by beta testing new features and conducting human factor reviews. Human factors testing was in its infancy. And of course, modularity and reuse of code and information was just being taken seriously. Object-oriented programming, and even object-oriented writing was put into play like never before. Here’s my paper on that from 1993: https://ieeexplore.ieee.org/document/593893/ – So I hope this began to answer your apt question, which I read as “does this really work in real life.” I’ve got many more examples, but perhaps best to save them for the book 🙂