Task Planning using Microsoft Project

  Watch Project Planning using Microsoft Project Project Management Institute (PMI)® Professional Development Units (PDUs): This short video is NOT eligible for PMI® PDU credit. Event Description: In this video viewers will learn how to plan out their tasks within Microsoft Project. They will learn how to add tasks to a schedule, the difference between Auto and Manually…

3 Task Tips

1. Before entering any tasks, you have to specify how many work hours equal a workday by using option Hours per Day on the tab Schedule (ribbon File, item Options). Microsoft Project uses this setting to convert between time units; it is the time unit conversion factor. All durations will be recalculated when you change this…

4 Handy Microsoft Project Scheduling Tips

1. When you schedule electronically, you should not enter start or finish dates for tasks. If you use Microsoft Project to simply capture dates and only dates, you may as well use Microsoft Excel instead. With MS Project, you enter durations and dependencies instead of dates to create a forecast model. The software then calculates start…

What You Need to Know about Project Server 2010 Service Pack 1, Part 1

The release of Service Pack 1 for Project Server 2010 and Microsoft SharePoint marks a major milestone in the product development lifecycle. All fixes prior to the June 2011 Cumulative Update (CU) are included in SP1. In addition, there are some key enhancements included in SP1 that users will appreciate, from new browser support to…

Please enter your email to continue viewing