Nonworking Time Calendar

To change the working time for a specific day, click on the day in the calendar and then click on the "Working hours" button. In the "Working hours" dialog box, you can specify the start time, end time, and break time for the day. You can also specify whether the day is a holiday or a non-working day.

To change the working time for a range of days, click on the first day of the range and then hold down the Shift key while clicking on the last day of the range. Then, click on the "Working hours" button. In the "Working hours" dialog box, you can specify the start time, end time, and break time for the range of days. You can also specify whether the range of days is a holiday or a non-working day.

To change the working time for the entire calendar, click on the "Calendar" tab in the ribbon and then click on the "Working time" button. In the "Working time" dialog box, you can specify the start time, end time, and break time for the entire calendar. You can also specify whether the calendar is a holiday or a non-working day.

Advanced Use of the Nonworking Time Calendar

Background In my previous article on Understanding the Nonworking Time Calendar, I showed you how to apply an alternate base calendar as the Project Calendar and the Nonworking Time Calendar for a pro...