1. At ProjectPro, we created a guideline that we call the 1%-10% rule. The duration of any lowest-level task should be between a minimum and maximum duration. The minimum duration is 1% of the project...
In the active project plan file, apply the proper command sequence to open the File Properties dialog box. In Project 2013, that’s File > Info > Project Information > Advanced Propertie...
So far in this series I’ve illustrated two very powerful features of Project 2007: Multiple Undo / Redo and Change Highlighting. In this article I examine cost and budget resources and how they might ...