Applying Details to the Task Form View

In a recent blog post article, I discussed how to apply and use the Task Entry view. This view, by the way, is a combination view or “split” view that includes the Gantt Chart view in the top pane and the Task Form view in the bottom pane. What I did not explain in my…

Using the Task Entry View

In my humble opinion, I believe the Task Entry view is one of the most powerful views available in Microsoft Project. Using this view, you can take complete control over the software’s scheduling engine while you assign resources to tasks in your project schedule. By now, you might be asking yourself, “Task Entry view? I…

Schedule a Task to Start As Late As Possible Based on the Start Date of Another Task

Problem Description I answered an interesting question recently in the Microsoft Answers user forum for Microsoft Project users. The user who asked the question stated that she was new to Microsoft Project. She indicated that she is managing a construction project and wanted to know the latest possible date she could order wood flooring so…

View All Predecessors and Successors for a Task

A question in the Project Standard and Professional user forum caught my eye recently. I answered the user’s question in the forum and then decided to blog about it. The user asked how to create a view in which he could select any task and see all of the task’s Predecessors and Successors, along with…

Critical Path, Criticality Analysis, and Criticality Index

Imagine the following scenario. You are in charge of managing a big match in a stadium. The venue can hold over 100,000 people. The audience is as passionate about watching, as their favorite players are about playing. Any untoward incident can create problems. You want to have the security, monitoring, and all other aspects of…

Four Tips to Ensure Accurate Project Status

Microsoft Project is a powerful project management tool. That’s what it is – a tool. Its dashboards and views are an agent for successful status communication, but the highlighted information is only as good as the accuracy of the user’s data. What type of information is important to ensure an accurate project status? Where do…

Adding a Current Tasks Flag

It is important to keep your project team focused on current and near-term tasks. If you want to send out a weekly update to your project team, showing which tasks are active, but incomplete, or scheduled to start in the next week, it would help to have a flag that automatically identifies those tasks for…

Ask the Expert: Import Excel Data into Project – Tips & Troubleshooting

MS Project’s import/export function is not as clear cut as it seems, but if you follow some of the tips below the procedure should work more smoothly for you. The design of the data, the wording of the Excel tabs, column headings, and options all need to be considered to have import/export working in a…

Managing Negative Slack: Dos and Don’ts

Much has been written about Critical Path, Slack, Constraints, and the various forms of Duration and Dependencies. But, have you looked for Negative Slack? This is generally defined as the amount of time required to complete a task or project beyond its scheduled finish date. Think of it as the minimum amount of time to…

Keep Your Outlook Calendar Up to Date with Your Microsoft Project Tasks Using the P2O Application

Project Management Institute (PMI)® Professional Development Units (PDUs): This Webinar is eligible for 1 PMI® PDU in the Technical category of the Talent Triangle. Event Description: Outlook is the tool we all use to manage our day to day corporate and personal tasks, and yet as Project Managers or Team Members we’re also expected to…