Taking the PMP® Exam? A Sample Question

Question

Your company has just been awarded the contract for a research project. The CEO of your company has asked you, as the project manager, to create the project charter and send it to her so that she can review and approve it. To create the project charter, you need the project’s statement of work (SOW). What should you do?

A.) Create the SOW yourself since you are the project manager

B.) Look for the SOW in your organizational process assets (OPAs)

C.) Ask your customer to provide you with the SOW

D.) Ask your CEO to provide you with the SOW

 

Hint: Part of a project manager’s role is to collaborate with the customer and understand the details of the project.

 

Answer and Explanation

The correct answer is C, Ask your customer to provide you with the SOW.

As the project manager, you should request the project’s procurement SOW directly from the buyer (i.e., your customer) to ensure you have the agreed upon SOW. Also, requesting the SOW from your customer demonstrates that you are proactive and encourages collaboration.

 

Reference: A Guide to the Project Management Body of Knowledge – Sixth Edition, Project Management Institute Inc., 2017, Page(s) 77, 477

This sample question was provided by The PM Exam Simulator. All questions are updated to the latest A Guide to the Project Management Body of Knowledge (PMBOK® Guide) standard.

 

 

Disclaimer and Copyright Statement
PMI, PMP, CAPM, PgMP, PMI-ACP, PMI-SP, PMI-RMP and PMBOK are trademarks of the Project Management Institute, Inc. PMI has not endorsed and did not participate in the development of this publication. PMI does not sponsor this publication and makes no warranty, guarantee or representation, expressed or implied as to the accuracy or content. Every attempt has been made by OSP International LLC to ensure that the information presented in this publication is accurate and can serve as preparation for the PMP certification exam. However, OSP International LLC accepts no legal responsibility for the content herein. This document should be used only as a reference and not as a replacement for officially published material. Using the information from this document does not guarantee that the reader will pass the PMP certification exam. No such guarantees or warranties are implied or expressed by OSP International LLC.

Next Webinar

Task Types Demystified.

Written by Cornelius Fichtner
Cornelius Fichtner, PMP is a noted PMP expert. He has helped over 47,000 students prepare for the PMP Exam with The Project Management PrepCast and The PM Exam Simulator.
Share This Post
Have your say!
00
1 Comment
  1. PMP exam questions would be a great recurring feature in the weekly newsletter. (It’s a good review for those of us that already have our PMP.)

Leave a Reply