Loading...
Quick Links

2 activity must have the same duration

Home Forums Discussion 2 activity must have the same duration

Viewing 4 posts - 1 through 4 (of 4 total)
  • Author
    Posts
  • #404212 Reply
    andrea de ligio
    Guest

    Good morning,

    I just started to use this program and I wanted to ask you this:

    I am two or more activities (fixed units) starting at different times (the start is governed by various predecessors). I would like to set the duration of activity number 03-05-18 and 15 we all have the same duration of activity 2. without changing the predecessors.

    It’s possible?

    #404229 Reply
    Larry ChristofaroLarry Christofaro
    Participant

    Andrea, sorry but I can’t understand the question. Setting duration the same on multiple tasks is pretty simple and has nothing to do with predecessors. Use the duration field, not the start or finish. If that doesn’t help then please provide more details and I can see if I can help.

    #404239 Reply
    andrea de ligio
    Guest

    sorry for my English…

    I wish that by changing the duration of an activity, even automatically would change the lives of other activities.

    for exemple:
    activity A: 10 gg
    activity B: 10 gg

    if i change the duration of activity A in 20gg –> automatically the duration of activity B became 20gg

    #404272 Reply
    Larry ChristofaroLarry Christofaro
    Participant

    Not really. There is a feature called Hammock Tasks that can do this but it is highly recommended not to use in general (not very stable). I’m only mentioning this in case you run across this somewhere and want to try it.

Viewing 4 posts - 1 through 4 (of 4 total)
Reply To: 2 activity must have the same duration
Your information:




− 1 = 5