2 Tasks, 1 Project; Task A is not by working days but Task B is working days

Home Forums Discussion Forum 2 Tasks, 1 Project; Task A is not by working days but Task B is working days

Viewing 2 reply threads
  • Author
    Posts
    • #418606
      Griffin P
      Guest

      Task A lasts X long (24/7 scheduling)
      Task B lasts Y long (working days only)

    • #418613
      Daryl Deffler
      Guest

      Griffin
      Not sure what the question is, but I’ll assume its how to do this.
      Define your normal work calendar, for example, M-F 8-5. Make that the project calendar and by default, Task B will use that calendar since you didn’t override it at the task level.
      Create a 24×7 calendar and on Task A, attach that 24×7 calendar to that task.

      Hope that helps

    • #418614
      Griffin P
      Guest

      Daryl,

      I realized I didn’t put an ask of any sort, thank you for decoding my post! Very helpful!