Loading...
Quick Links

Ability to Reference Task B's Field Contents in Task A

Home Forums Discussion Ability to Reference Task B's Field Contents in Task A

Viewing 1 post (of 1 total)
  • Author
    Posts
  • #315377 Reply
    Scott Brunton
    Participant

    Greetings!

    I would like to be able to reflect the %Complete of one task in a, say, Number field in another task. Can this be accomplished with a Formula that uses the UID of the task being referenced?

    Here is the ‘why’ … I have built a Summary section at the top of the schedule to reflect progress made in a section within the body of the schedule. In particular, I would like to pull the %Complete from the Summary task of that section and drop it into a milestone task at the top. Can be very useful when building Custom Reports.

    Thanks!

Viewing 1 post (of 1 total)
Reply To: Ability to Reference Task B's Field Contents in Task A
Your information: