  • #417363 Reply
    Gayathry
    Guest

    Hi, Im a scheduler in construction field, I have prepared resource loaded schedule (cost, work, material) in MS projects, while tracking through % complete I find the actual cost column is not getting updated whereas the material & work gets updated. One more finding is that when a particular activity is having only one resource ie cost then actual cost gets updated, but if the activity is having more than one resource (eg cost & work) then actual cost doesnt get updated. Kindly clarify

    #417364 Reply
    Larry ChristofaroLarry Christofaro
    Participant

    Hi Gayathry, the behavior you are getting is by design. Best practice and Microsoft recommendation is not to combine cost and other resources on the same task because of the behavior differences. Hope that helps…

    #417366 Reply
    Carlos Santos
    Guest

    Hi Gayathry

    I have had that problem too.
    So I looked for a solution and found this article on Mpug.
    Larry is right.

    https://www.mpug.com/articles/using-cost-resources-best-practice/