Loading...
Quick Links

Actual Work is more than Work

Home Forums Discussion Actual Work is more than Work

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #117063 Reply
    Annie
    Guest

    I’m working on a contract and staying under the budget. I used the Work column to enter the planned hours for each task and I use the Actual Work column to track how many hours have been spent on that task. One task’s Actual Work is more than the Work originally planned. When I update the Actual Work, MSProject updates the Work column to match. How can I show on my plan that the task took longer than planned and that it went over the time budget?

    #117070 Reply
    Chad Olson
    Participant

    You set a baseline. Then track Baseline Work against your Work. Think of the work value as Estimate to Complete work. It will always change depending on Actual Work entered or Remaining Work entered.

Viewing 2 posts - 1 through 2 (of 2 total)
Reply To: Actual Work is more than Work
Your information:




− 1 = 3