Added Resource Vacation Time to a Project

Home Forums Discussion Added Resource Vacation Time to a Project

  • This topic has 2 replies, 3 voices, and was last updated 2 years, 1 month ago by Norman Christensen.
Viewing 3 posts - 1 through 3 (of 3 total)
  • Author
    Posts
  • #414421 Reply

    Hello,

    We are currently using Project Online with MS Project 2013. A Standard calendar has been created on the Project Online side and is used for all resources.
    Some of the PMs would like to add vacation time for resources as non-working time. How can this be done so that the PMs can do these changes themselves?

    Thanks.. Larry

    #414424 Reply
    Larry ChristofaroLarry Christofaro
    Participant

    Unfortunately not without the ability to edit enterprise resources. I’ve suggested using a special vacation project with a higher priority for customers using resource leveling. You can still use that for other customers but it won’t reduce demand for those periods. Not great news but that’s the way it works. Resources belong to the enterprise and not a particular project. Hope that helps…

    #414425 Reply
    Norman Christensen
    Guest

    Thanks. That is what I thought.

Viewing 3 posts - 1 through 3 (of 3 total)