Allocation of multiple resources to one task

Home Forums Discussion Allocation of multiple resources to one task

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #297496 Reply
    Matt Matulewicz
    Guest

    I assigned two resources at differing % to one task of 142 hours. Will be working to break it down under 80 later.
    The problem I have is at the end of the task, one of the resources shows no allocation for a period of 5 weeks.
    Why won’t MS Project 2010 evenly allocate the resources to the task evenly?

    #300797 Reply
    Sai Prasad
    Participant
    • Community Leader
    • Forum Pro

    Matt – Since you have hinted one of the resource has no allocation for a period of 5 weeks, check if there are exceptions (holidays) set for this resource. What is the Task type and Effort driven? It would be good if you can provide a screenshot of this assignment?

Viewing 2 posts - 1 through 2 (of 2 total)