Anyone having troubles with Timesheets in Project Server 2010?

Home Forums Discussion Forum Anyone having troubles with Timesheets in Project Server 2010?

Viewing 2 reply threads
  • Author
    Posts
    • #4920
      Native Linum
      Keymaster
      I’m having troubles with entering actual time on some project tasks.  The administration time is fine and some project tasks are fine.  There is assignments created for the resource in that time period.  Any suggestions on where to look?
    • #6220
      Native Linum
      Keymaster
      Good Afternoon Sandy,
      Are you still experiencing Timesheet issues with Project Server 2010?
      Let us know.
      Also – what Cumulative Update are you on?
      Looking forward to providing assistance.
      -Jacques
    • #6272
      Native Linum
      Keymaster
      Sandy,
      Check to see if the tasks are manually scheduled.  If they are manually scheduled, you cannot enter actual time on the task.  Only auto-scheduled tasks accept actual time.