Loading...
Quick Links

Application of Islamic weekend

Home Forums Discussion Application of Islamic weekend

Viewing 4 posts - 1 through 4 (of 4 total)
  • Author
    Posts
  • #400717 Reply
    Stergios Kokkoris
    Guest

    Dear friends,

    I set, according to Islamic calendar the Friday as non working day for the whole schedule, but I want to do a couple of Fridays.
    How can I do that?
    Thank you in advance for your help.

    kind regards

    Stergios Kokkoris

    #400718 Reply
    Stergios Kokkoris
    Guest

    Sorry,

    I resend my inquiry. It sent incomplete by accident.

    Dear friends,

    I set, according to Islamic calendar the Friday as non working day for the whole schedule, but I want to set a couple of Fridays as working days.
    How can I do that?
    Thank you in advance for your help.

    kind regards

    Stergios Kokkoris

    #400737 Reply
    Julie Sheets
    Guest

    As odd as it sounds, you’d create an exception to make the occassional Friday a working day. Assuming you have altered the calendar to make all Fridays non-working, open the calendar and select the Friday you’d like to work. Click the Exceptions tab in the Change Working Time dialog. Give the exception a name, click in the start or finish field to the right. Click the Details button. Click the Working times option and enter the working times for that day. Repeat as needed for other days.

    #401042 Reply
    Stergios Kokkoris
    Guest

    Thank you very much Julie, I appreciate your help

Viewing 4 posts - 1 through 4 (of 4 total)
Reply To: Application of Islamic weekend
Your information:




62 − = 54