Assigning resources full time for a portion of the task

Home Forums Discussion Assigning resources full time for a portion of the task

Viewing 2 posts - 1 through 2 (of 2 total)
  • Author
    Posts
  • #297659 Reply
    Harold Gamblin
    Guest

    New to Project and need advice. I would like to define the work (hours) required as well as the start and completion dates.
    Then I would like to assign resources (people) intermittently to the task full time – example task will require 60 hours of work but I would like to assign a resource for the next two days only contributing 16 hours leaving 44 hours still to completion. How (or can) I achieve this senario where Project will still honor my dates and total work definitions?

    #300799 Reply
    Sai PrasadSai Prasad
    Participant
    • Community Leader
    • Forum Pro

    Harold – You can ask Project to respect the Start and Finish date by changing the Task Mode to Manually Scheduled. This will ensure as you increase/decrease work the start and finish won’t change. Now change your view to Task Usage (View ribbon). In Time-phased data (right side) enter the 8 hours for the first two days and make edits for the remaining days left.

Viewing 2 posts - 1 through 2 (of 2 total)