  • #65054 Reply
    fabio
    Guest

    Hi everybody. I am at the beginning with MS Project.

    Somebody could tell me how come in some files, in the main ribbon, buttons for automatic and manual schedule are highlighted and in others they aren’t?

    Sometimes this cause me the impossibility to switch the way I let the task works with dates.

    Thank you.

    #77590 Reply
    Sai Prasad
    Participant
    • Community Leader
    • Forum Pro

    Fabio – Task mode feature was introduced in Project 2010. Using this feature you can ask Project to calculate automatically or not (you can insert a column Task Mode). If you open project file created in Project 2007 or earlier version, Task mode is not supported and hence you see these buttons are disabled and also on the title of Project will be something like FileName[Compatibility Mode]. To get this right, save the file in Project 2010 format to support this feature.

    #110117 Reply
    Jack Fox
    Guest

    Spam Alert:

    Home › Forums › Discussion › AUTOMATIC SCHEDULE

Viewing 3 posts - 1 through 3 (of 3 total)
Reply To: AUTOMATIC SCHEDULE
Your information:




92 − = 91