    Can some one advise on how to change Saturday to a work day for the whole life span of the project?

     

    From Member –  Bob Kunhardt

    #4664 Reply
    Anonymous
    Inactive

    I have it now – acually Bonnie Biofore helped me out

    You go to the “Work Weeks” tab in the “Change Working Time” window (Project Tab) – enter work hours for Saturday and that does it.

    Thanks Bonnie!