Baseline work not visible in Task usage view

Home Forums Discussion Forum Baseline work not visible in Task usage view

Viewing 1 reply thread
  • Author
    Posts
    • #61037
      Sune Schrøder Rasmussen
      Guest

      Hi all

      I want to have baseline work distrubuted across weeks in task usage view.

      If I go to the task view I’m able to see the work distributed across week and I want to have the same view for baseline work. I’m able to choose the Baseline work in details but no data are shown.

      br. sune

    • #77598
      Sai Prasad
      Participant

      Hi – Looks like you have updated the work field or assigned resources to the tasks after baseline the plan. Also, check the baseline fields in Baseline table of Gantt Chart. If the baseline work is 0, my guess is right. Then, you need to redo baseline the project and then record the actuals.

Viewing 1 reply thread
  • You must be logged in to reply to this topic.