Best practice for entering work on a task

Home Forums Discussion Forum Best practice for entering work on a task

Viewing 2 reply threads
  • Author
    Posts
    • #29245
      Anonymous
      Inactive

      I am in the initial planning stages of my Project Plan (Project 2007 server).

      I have found 2 ways to enter work for the task.

      Create task, add work and add resource name at the same time.
      Create task, add work without adding the resource name.  Add the resource name later.

      I typically use method 1, but in my current situation I would like to define the tasks and work, and fill in the resource later.

      I notice that the tasks behave a little different.

      With method 1 if at a later time I delete the resource, the work is deleted with it.

      With method 2 if at a later time I delete the resource, the work remains.

      Am I going to run into problems with method 2?

      Thanks.

       
       
       

    • #29266
      John Riopel
      Participant

      You don’t mention the task type when you perform these two options?   When adding a resource to a task, Microsoft Project looks at the task type and also whether is a resource already assigned, as well as the effort driven flag and performs the appropriate calculation based on these settings for the task.  So I know this will sound a little lame but it will depend on the result you are trying to achieve when working with resources.

    • #29277
      Sai Prasad
      Participant

      I agree with John that based on the task type field the behavior changes.

      By default, the task type is set to Fixed Unit (you can open the task and see the Advanced tab, you will notice the Task Type is Fixed Units). In your case you have added work for a task and then assigned the resource. Now being a fixed units task, the duration will be adjusted based on the work and the resource units. If you remove the resource from the task, in other words when you decrease the resource units the work is reduced to fill the task duration and hence the work is reduced to 0.

      If you want the task work to be fixed and the duration to be flexible, change the Task Type to Fixed Work. If you are assigning multiple resources to the task and want task work to be distributed across the task duration such that the hours assigned each resource per day is less then set Task Type to Fixed Duration and check Effort Driven (in Advanced tab) – that is Task Work is also fixed

      Hope this helps