  • #418215 Reply

    I’m using MS Project Online desktop client MSO (16.0.11929.20762) 32-bit

    I have a master project with 4 subprojects. I created a Resource Pool.mpp project with a single resource, saved it on my sharepoint server alongside my 5 projects, and tried to add it but it doesn’t appear in the “Use Resources From” dropdown menu of the Share Resources dialog.

    So I opened a new project. THAT appears in the dropdown menu. If I try to use it as resource pool, however I get an error dialog stating “We can’t use this resource pool. The project and the resource pool need to first be saved in the same place.” When I save it to my sharepoint drive, it TOO, becomes invisible as a resource pool.

    I tried saving a copy of one of my subprojects in the same sharepoint directory and deleted all of the tasks I still don’t seem to be able to use it as a resource pool (it doesn’t appear when I try to choose a resource pool).

    I AM able to choose one of my subprojects as a resource pool FROM my resource pool project – which is backwards.

    Any suggestions?